Will Boeing 777X Certification Slide Past 2027 Due to New FAA Demands?
Key Points
- 1The FAA is reportedly requesting new safety enhancements for the Boeing 777X flight control system, risking a further delay past the 2027 entry-into-service target.
- 2The 777X program is already seven years behind its original 2020 EIS date, largely due to post-737 MAX regulatory scrutiny and technical issues.
- 3Boeing recorded a $4.9 billion charge in Q3 2025 due to the program's development and delivery delays.
- 4Major customers like Emirates and Lufthansa face continued uncertainty in their long-haul fleet planning.
Sources familiar with the matter report Boeing is facing further delays in its 777X program. The Federal Aviation Administration (FAA) is reportedly requesting additional safety enhancements. This new scrutiny focuses on the aircraft's critical 777X flight control system. The regulatory pressure could push the 777-9 entry-into-service date past the current 2027 target.
Background on the 777X Program
The 777X is a key new widebody jet delay for Boeing. It is an upgraded version of the successful 777 widebody. The aircraft features new General Electric GE9X engines and folding wingtips. The original plan was for the 777-9 to enter service in 2020. However, the program has faced multiple setbacks over the years. These issues included engine-mounted thrust link failures and regulatory scrutiny.
Increased oversight followed the 737 MAX grounding. This led to a more rigorous aircraft certification process. The FAA and European Union Aviation Safety Agency (EASA) demanded changes. They required more data and a new certification approach. Boeing announced the revised 2027 EIS target in late 2025. This was seven years later than the initial expectation.
The Core Regulatory Hurdle
The latest reported delay centers on the 777X flight control system. The system's complexity is a major focus for the FAA. Early in the program, the aircraft experienced an "uncommanded pitch event" during a test flight. This incident raised serious concerns about the flight control software. The FAA has also focused on the Common Core System (CCS) avionics. This critical system manages multiple airplane functions. The agency required Boeing to provide conclusive evidence on software and hardware fixes.
In late 2025, Boeing received a key approval. The FAA granted Type Inspection Authorization (TIA) Phase 3. This milestone covered avionics and other substantive systems. However, the new reported request for FAA safety enhancements suggests new issues or deeper scrutiny. This indicates the Boeing 777X certification remains a significant challenge.
Industry Impact and Airline Concerns
The continued delays are creating major headaches for airlines. Key customers have been waiting years for the new widebody jet. Launch customer Lufthansa and major buyer Emirates have had to adjust their airline delivery schedules. Emirates President Sir Tim Clark has previously voiced frustration over the program's lack of visibility. The airline relies on the 777X for its long-haul fleet strategy.
- Financial Toll: Boeing recorded a $4.9 billion charge in Q3 2025. This charge was directly linked to the 777X development and delivery delays.
- Fleet Planning: Airlines must now use older aircraft for longer. They are also considering alternatives from competitor Airbus.
- Market Share: Delays allow the Airbus A350 to gain a stronger foothold in the long-range market segment.
Path Forward for Boeing
Boeing maintains its commitment to safety as its top priority. The company is working closely with the FAA to meet all new requirements. The focus is on the remaining TIA phases. These final phases involve compliance checks and documentation. The company must demonstrate a robust and reliable 777X flight control system. The goal is to avoid any similar future systemic issues. The outcome of this regulatory review is vital for the future of the commercial aviation news cycle and the entire widebody market. You can find more updates on this story and other commercial aviation news at flying.flights.
- New Certification Era: The new regulatory environment requires more documentation. It also demands greater transparency from the manufacturer.
- Customer Relations: Rebuilding trust with major customers is now paramount. This includes providing clear airline delivery schedules.
- Safety Culture: The delays underscore the need for a stronger safety culture at Boeing.
Topics
Written by
Ujjwal SukhwaniAviation News Editor & Industry Analyst delivering clear coverage for a worldwide audience.
View ProfileYou Might Also Like
Discover more aviation news based on similar topics
Why is the Boeing 777X first delivery now pushed to late 2026?
Boeing has again delayed the 777X first delivery to late 2026, citing ongoing FAA certification issues, impacting key customers like Emirates.
Will Boeing's 737 MAX 10 Clear Final FAA Certification Hurdles?
The FAA approved the largest Boeing 737 MAX 10 variant to enter the second phase of flight testing, but a critical engine deicing issue remains unresolved.
Why Delta Air Lines is Adding Up to 60 Boeing 787 Dreamliners to Its Fleet.
Delta Air Lines has confirmed a major order for up to 60 Boeing 787 Dreamliners, signaling a significant investment in its long-haul fleet modernization and global network expansion.
How Will ICAO's New Global Standard Reshape Future Aircraft Emissions?
ICAO adopted a more stringent global CO2 emissions standard for aircraft, requiring compliance for new designs by 2027 and in-production models by 2030.
Boeing Achieves Seven-Year High in Deliveries; Will Production Rate Accelerate?
Boeing is set to announce its highest annual airplane deliveries since 2018, driven by the 737 MAX, and will outline plans for a further production rate increase this month.
Airbus Closes A380 Program: Emirates Receives Final Superjumbo Delivery
Emirates received the final Airbus A380 superjumbo delivery (MSN 272) on December 16, 2021, marking the official end of the A380 production program.